The design team continually engages with the Woodstock Select Board to evaluate and adjust design approach and consider cost/value.
May 2023
Preliminary Engineering ReportJanuary 2024
Town of Woodstock Main WWTF Project Public PresentationJanuary 2024
CWSRF Loan ApplicationMarch 2024
Congressional Directed Spending Application
$2,500,000 for Green Energy & Efficiency ImprovementsMay 12, 2025
Revised Alternatives Presentation to Select BoardJune 2025
Revised Preliminary Engineering Report to include AGS Biological Process TechnologyNovember 15, 2025 from 10:00 am – 2:00 pm
Public Tours of the Main Wastewater Treatment FacilityJanuary 14, 2026 at 9 am at Abracadabra Coffee Co.
35 Wayside Rd, Woodstock, VT 05091
Public Information ForumJanuary 21, 2026 at 9 am at Mon Vert Cafe
28 Central St, Woodstock, VT 05091
Public Information ForumJanuary 28, 2026 at 9 am at Dreamscape Coffee
67 Central St, Woodstock, VT 05091
Public Information ForumFebruary 4, 2026 at 9 am at South Woodstock County Store
4800 South Rd, South Woodstock, VT 05071
Public Information ForumFebruary 11, 2026 at 9 am at Abracadabra Coffee Co.
35 Wayside Rd, Woodstock, VT 05091
Public Information ForumFebruary 18, 2026 at 9 am at Dreamscape Coffee
67 Central St, Woodstock, VT 05091
Public Information ForumFebruary 19, 2026 at 5 pm at Town Hall
Special Select Board Meeting/Public Information meetingFebruary 25, 2026 at 9 am at South Woodstock County Store
4800 South Rd, South Woodstock, VT 05071
Public Information ForumMarch 3, 2026
Bond VoteOctober 2026
Final Design & Permitting CompleteNovember 2026 – February 2028
Bid & Construction